Enabling the 1st Alignment of the Poniente Dock.

The works consisted of paving the first alignment of the Poniente Dock, which was not contemplated in the “Correction of the first alignment of the Poniente Dock” Project.

Work completed in May 1997, executing 11,200 m2 of 30 cm HP-40 concrete pavement. Thickness, 350 m2 of 13 cm HP-40 concrete pavement. Thickness, 650 m2 of 8 cm surface layer. Thick with hot mix, 200 m. of pipes and grid for rainwater collection, 50 m. of fiber cement pipe 400 series S-3, 200 m3 of reinforced concrete for foundation of crane rails, 450 m.l. of rolling rail and 1,250 m. of PVC 110 pipe for electrical conduit.

The total cost of the operation amounted to € 390,591.15