Port Authority

Consolidation of the Cañonero Dato dock.

The works consisted of the restoration of the Raymond-type piles and reticular forgings with prefabricated troughs executed at berths No. 2 and the ramp of No. 2 and No. 3 of the Cañonero Dato dock.

Work completed in October 1997, with the execution of 11,100 m2 of concrete structure protection, 1,250 m2 of repair and regeneration of the reinforced concrete structure and 620 m.l. injection of fissures.

The total cost of the operation amounted to € 344,926.12